Combined Cycle Uprate (531)

Combined Cycle Uprate is a 30.0 MW gas interconnection project in Penobscot, Maine with a current status of withdrawn. It is proposed to connect at EMERA Maine-Graham Station via 115kv.

30.0 MWCapacity
WithdrawnStatus
BHEMarket
GasTechnology

Project facts

Canonical nameCombined Cycle Uprate
Queue ID531
Statuswithdrawn
Source statusW
MarketBHE
TechnologyGas
Capacity30.0 MW
StateMaine
CountyPenobscot
Point of interconnectionEMERA Maine-Graham Station via 115kv
Requested (queue) date2015-02-27
Proposed in-service date2018-08-01
Operational date
Withdrawn date2018-04-05
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata