Council Bluffs - Fallow Avenue 345kV Line Tap (J1859)

Council Bluffs - Fallow Avenue 345kV Line Tap is a 200.0 MW wind interconnection project in Pottawattamie, Iowa with a current status of withdrawn. It is proposed to connect at Council Bluffs - Fallow Avenue 345kV Line Tap.

200.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameCouncil Bluffs - Fallow Avenue 345kV Line Tap
Queue IDJ1859
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity200.0 MW
StateIowa
CountyPottawattamie
Point of interconnectionCouncil Bluffs - Fallow Avenue 345kV Line Tap
Requested (queue) date2021-08-16
Proposed in-service date2024-09-15
Operational date2024-09-15
Withdrawn date2021-10-12
Developer
Utility / transmission ownerMIDAMERICAN ENERGY CO.

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata