Cudahy 115 kV Substation (GEN-2024-094)

Cudahy 115 kV Substation is a 200.0 MW wind interconnection project in Meade, Kansas with a current status of withdrawn. It is proposed to connect at Cudahy 115 kV Substation.

200.0 MWCapacity
WithdrawnStatus
KSMarket
WindTechnology

Project facts

Canonical nameCudahy 115 kV Substation
Queue IDGEN-2024-094
Statuswithdrawn
Source statusWITHDRAWN
MarketKS
TechnologyWind
Capacity200.0 MW
StateKansas
CountyMeade
Point of interconnectionCudahy 115 kV Substation
Requested (queue) date2025-03-01
Proposed in-service date2028-06-30
Operational date
Withdrawn date2025-08-28
Developer
Utility / transmission ownerSUNC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata