Cunningham 115kV (GEN-2023-GR4)
Cunningham 115kV is a 72.0 MW solar interconnection project in Lea County, New Mexico with a current status of active. It is proposed to connect at Cunningham 115kV.
72.0 MWCapacity
ActiveStatus
NMMarket
SolarTechnology
Project facts
| Canonical name | Cunningham 115kV |
|---|---|
| Queue ID | GEN-2023-GR4 |
| Status | active |
| Source status | IA FULLY EXECUTED/ON SCHEDULE |
| Market | NM |
| Technology | Solar |
| Capacity | 72.0 MW |
| State | New Mexico |
| County | Lea County |
| Point of interconnection | Cunningham 115kV |
| Requested (queue) date | 2023-07-05 |
| Proposed in-service date | 2026-05-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Xcel/SPS |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | active | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.