Dallesport Server Farm (L0664)

Dallesport Server Farm is a 1,000.0 MW other interconnection project with a current status of active. It is proposed to connect at Big Eddy Substation or Big Eddy-Chenowith No. 2 230 kV line.

1,000.0 MWCapacity
ActiveStatus
Market
OtherTechnology

Project facts

Canonical nameDallesport Server Farm
Queue IDL0664
Statusactive
Source statusSTUDY
Market
TechnologyOther
Capacity1,000.0 MW
State
CountyKlickitat
Point of interconnectionBig Eddy Substation or Big Eddy-Chenowith No. 2 230 kV line
Requested (queue) date2025-08-25
Proposed in-service date2029-10-01
Operational date
Withdrawn date
DeveloperPublic Utility District No. 1 of Cowlitz County
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.