Desert Claim (G105)

Desert Claim is a 159.0 MW wind interconnection project in Kittitas, Washington with a current status of withdrawn. It is proposed to connect at Covington-Columbia 230kV transmission line.

159.0 MWCapacity
WithdrawnStatus
WAMarket
WindTechnology

Project facts

Canonical nameDesert Claim
Queue IDG105
Statuswithdrawn
Source statusWITHDRAWN
MarketWA
TechnologyWind
Capacity159.0 MW
StateWashington
CountyKittitas
Point of interconnectionCovington-Columbia 230kV transmission line
Requested (queue) date2002-06-20
Proposed in-service date2009-10-01
Operational date
Withdrawn date
DeveloperenXco Northwest
Utility / transmission ownerBonneville Power Administration

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata