Duane Arnold 161 kV (R1012)
Duane Arnold 161 kV is a 640.0 MW generation interconnection project with a current status of operational. It is proposed to connect at Duane Arnold 161 kV.
640.0 MWCapacity
OperationalStatus
—Market
GenerationTechnology
Project facts
| Canonical name | Duane Arnold 161 kV |
|---|---|
| Queue ID | R1012 |
| Status | operational |
| Source status | Withdrawn |
| Market | — |
| Technology | Generation |
| Capacity | 640.0 MW |
| State | — |
| County | Linn County |
| Point of interconnection | Duane Arnold 161 kV |
| Requested (queue) date | 2021-09-30 |
| Proposed in-service date | 2023-07-01 |
| Operational date | 2023-07-01 |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Alliant Energy West |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-29 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.