East Fishkill (1122)
East Fishkill is a 205.0 MW battery interconnection project in Dutchess, New York with a current status of active. It is proposed to connect at Shenandoah 115kV.
205.0 MWCapacity
ActiveStatus
GMarket
BatteryTechnology
Project facts
| Canonical name | East Fishkill |
|---|---|
| Queue ID | 1122 |
| Status | active |
| Source status | 11 |
| Market | G |
| Technology | Battery |
| Capacity | 205.0 MW |
| State | New York |
| County | Dutchess |
| Point of interconnection | Shenandoah 115kV |
| Requested (queue) date | 2020-12-11 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | — |
| Developer | East Fishkill Storage 1, LLC |
| Utility / transmission owner | CHG&E |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | active | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata