EGC BESS II (1592)

EGC BESS II is a 200.0 MW battery interconnection project in Nassau, New York with a current status of withdrawn. It is proposed to connect at East Garden City 345kV bus.

200.0 MWCapacity
WithdrawnStatus
KMarket
BatteryTechnology

Project facts

Canonical nameEGC BESS II
Queue ID1592
Statuswithdrawn
Source status0
MarketK
TechnologyBattery
Capacity200.0 MW
StateNew York
CountyNassau
Point of interconnectionEast Garden City 345kV bus
Requested (queue) date2023-08-16
Proposed in-service date2024-05-31
Operational date
Withdrawn date
DeveloperJupiter Power LLC
Utility / transmission ownerNYPA

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.