ESJ PHASE II PROJECT (FKA RUMOROSA WIND ENERGY PHASE II PROJECT) (183)

ESJ PHASE II PROJECT (FKA RUMOROSA WIND ENERGY PHASE II PROJECT) is a 300.0 MW wind interconnection project with a current status of withdrawn. It is proposed to connect at East County (ECO) Substation 230kV.

300.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameESJ PHASE II PROJECT (FKA RUMOROSA WIND ENERGY PHASE II PROJECT)
Queue ID183
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologyWind
Capacity300.0 MW
StateMX
CountyBaja California
Point of interconnectionEast County (ECO) Substation 230kV
Requested (queue) date2007-03-05
Proposed in-service date
Operational date
Withdrawn date2017-10-10
Developer
Utility / transmission ownerSDGE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.