Evergy Tap the La Cygne to Stillwel 345 kV Line (GEN-2021-030)

Evergy Tap the La Cygne to Stillwel 345 kV Line is a 510.3 MW solar interconnection project in Linn Ks And Bates Mo, Kansas with a current status of active. It is proposed to connect at Evergy Tap the La Cygne to Stillwel 345 kV Line.

510.3 MWCapacity
ActiveStatus
KSMarket
SolarTechnology

Project facts

Canonical nameEvergy Tap the La Cygne to Stillwel 345 kV Line
Queue IDGEN-2021-030
Statusactive
Source statusIA FULLY EXECUTED/ON SUSPENSION
MarketKS
TechnologySolar
Capacity510.3 MW
StateKansas
CountyLinn Ks And Bates Mo
Point of interconnectionEvergy Tap the La Cygne to Stillwel 345 kV Line
Requested (queue) date2021-05-14
Proposed in-service date2029-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerKCPL

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.