Fair Haven Biomass (330)

Fair Haven Biomass is a 33.0 MW other interconnection project in Rutland, Vermont with a current status of withdrawn. It is proposed to connect at CVPS 46 kV Castleton - Fair Haven.

33.0 MWCapacity
WithdrawnStatus
VTMarket
OtherTechnology

Project facts

Canonical nameFair Haven Biomass
Queue ID330
Statuswithdrawn
Source statusW
MarketVT
TechnologyOther
Capacity33.0 MW
StateVermont
CountyRutland
Point of interconnectionCVPS 46 kV Castleton - Fair Haven
Requested (queue) date2010-05-10
Proposed in-service date2016-03-30
Operational date
Withdrawn date2015-06-09
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata