FERMI Storage Project is a 248.0 MW battery interconnection project in Monroe, Michigan with a current status of active. It is proposed to connect at Enrico-Brownstown 345kV.

248.0 MWCapacity
ActiveStatus
MISOMarket
BatteryTechnology

Project facts

Canonical nameFERMI Storage Project
Queue IDE0008
Statusactive
Source statusactive
MarketMISO
TechnologyBattery
Capacity248.0 MW
StateMichigan
CountyMonroe
Point of interconnectionEnrico-Brownstown 345kV
Requested (queue) date2025-08-06
Proposed in-service date2028-06-02
Operational date
Withdrawn date
DeveloperDTE Electric
Utility / transmission ownerDTE Electric Company

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.