Filer City 138 kV Substation (J914)

Filer City 138 kV Substation is a 30.0 MW gas interconnection project in Manistee County, Michigan with a current status of withdrawn. It is proposed to connect at Filer City 138 kV Substation.

30.0 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical nameFiler City 138 kV Substation
Queue IDJ914
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyGas
Capacity30.0 MW
StateMichigan
CountyManistee County
Point of interconnectionFiler City 138 kV Substation
Requested (queue) date2017-06-16
Proposed in-service date2019-10-01
Operational date2019-10-01
Withdrawn date2019-01-09
Developer
Utility / transmission ownerMETC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.