Finney 345kV (GEN-2010-052)

Finney 345kV is a 301.3 MW wind interconnection project in Haskell County, Kansas with a current status of withdrawn. It is proposed to connect at Finney 345kV.

301.3 MWCapacity
WithdrawnStatus
KSMarket
WindTechnology

Project facts

Canonical nameFinney 345kV
Queue IDGEN-2010-052
Statuswithdrawn
Source statusWITHDRAWN
MarketKS
TechnologyWind
Capacity301.3 MW
StateKansas
CountyHaskell County
Point of interconnectionFinney 345kV
Requested (queue) date2010-09-30
Proposed in-service date
Operational date
Withdrawn date2012-01-16
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata