Fortistar VP (0090)

Fortistar VP is a 79.9 MW gas interconnection project in Richmond, New York with a current status of withdrawn. It is proposed to connect at Fresh Kills 138kV.

79.9 MWCapacity
WithdrawnStatus
JMarket
GasTechnology

Project facts

Canonical nameFortistar VP
Queue ID0090
Statuswithdrawn
Source status0
MarketJ
TechnologyGas
Capacity79.9 MW
StateNew York
CountyRichmond
Point of interconnectionFresh Kills 138kV
Requested (queue) date2001-03-20
Proposed in-service date2009-05-27
Operational date
Withdrawn date
DeveloperFortistar Power Marketing, LLC
Utility / transmission ownerCONED

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.