Gallagher to Twinning 138kV (J2732)

Gallagher to Twinning 138kV is a 250.0 MW solar interconnection project in Ogemaw, Michigan with a current status of withdrawn. It is proposed to connect at Gallagher to Twinning 138kV.

250.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameGallagher to Twinning 138kV
Queue IDJ2732
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity250.0 MW
StateMichigan
CountyOgemaw
Point of interconnectionGallagher to Twinning 138kV
Requested (queue) date2022-09-15
Proposed in-service date2025-12-06
Operational date2025-12-06
Withdrawn date2025-08-01
Developer
Utility / transmission ownerMETC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata