Graceton 230 kV (AG2-587 - moved to TC2)

Graceton 230 kV is a 50.0 MW solar interconnection project in Harford, Maryland with a current status of withdrawn.

50.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameGraceton 230 kV
Queue IDAG2-587 - moved to TC2
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity50.0 MW
StateMaryland
CountyHarford
Point of interconnection
Requested (queue) date2021-03-31
Proposed in-service date2024-06-01
Operational date
Withdrawn date2025-07-07
Developer
Utility / transmission ownerBGE

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata