GRDA1 to CLARMR 5 161kV line (GEN-2017-061)

GRDA1 to CLARMR 5 161kV line is a 101.5 MW solar interconnection project in Mayes County, Oklahoma with a current status of operational. It is proposed to connect at GRDA1 to CLARMR 5 161kV line.

101.5 MWCapacity
OperationalStatus
OKMarket
SolarTechnology

Project facts

Canonical nameGRDA1 to CLARMR 5 161kV line
Queue IDGEN-2017-061
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketOK
TechnologySolar
Capacity101.5 MW
StateOklahoma
CountyMayes County
Point of interconnectionGRDA1 to CLARMR 5 161kV line
Requested (queue) date2017-05-28
Proposed in-service date—
Operational date2021-12-01
Withdrawn date—
Developer—
Utility / transmission ownerGRDA

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-10operational_date—2021-12-01medium
2026-09-10proposed_online_date2026-08-31—medium
2026-09-10statusactiveoperationalhigh
2026-07-31new_project—activehigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.