GRDA1 to CLARMR 5 161kV line (GEN-2023-SR27)

GRDA1 to CLARMR 5 161kV line is a 101.5 MW battery interconnection project in Mayes County, Oklahoma with a current status of active. It is proposed to connect at GRDA1 to CLARMR 5 161kV line.

101.5 MWCapacity
ActiveStatus
OKMarket
BatteryTechnology

Project facts

Canonical nameGRDA1 to CLARMR 5 161kV line
Queue IDGEN-2023-SR27
Statusactive
Source statusIA FULLY EXECUTED/ON SCHEDULE
MarketOK
TechnologyBattery
Capacity101.5 MW
StateOklahoma
CountyMayes County
Point of interconnectionGRDA1 to CLARMR 5 161kV line
Requested (queue) date2023-07-12
Proposed in-service date2028-06-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerGRDA

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata