Great Bend - Circle 230kV line (GEN-2019-068)

Great Bend - Circle 230kV line is a 50.0 MW battery interconnection project in Barton, Kansas with a current status of active. It is proposed to connect at Great Bend - Circle 230kV line.

50.0 MWCapacity
ActiveStatus
KSMarket
BatteryTechnology

Project facts

Canonical nameGreat Bend - Circle 230kV line
Queue IDGEN-2019-068
Statusactive
Source statusIA FULLY EXECUTED/ON SUSPENSION
MarketKS
TechnologyBattery
Capacity50.0 MW
StateKansas
CountyBarton
Point of interconnectionGreat Bend - Circle 230kV line
Requested (queue) date2019-05-24
Proposed in-service date2029-08-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerSUNC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata