Green Apple (L0471)

Green Apple is a 35.0 MW other interconnection project in Whatcom, Washington with a current status of withdrawn. It is proposed to connect at Bellingham Substation 115 kV.

35.0 MWCapacity
WithdrawnStatus
WAMarket
OtherTechnology

Project facts

Canonical nameGreen Apple
Queue IDL0471
Statuswithdrawn
Source statusWITHDRAWN
MarketWA
TechnologyOther
Capacity35.0 MW
StateWashington
CountyWhatcom
Point of interconnectionBellingham Substation 115 kV
Requested (queue) date2019-12-17
Proposed in-service date2023-01-01
Operational date
Withdrawn date
DeveloperPublic Utility District No. 1 of Cowlitz County
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata