Green Apple Solar (1097)
Green Apple Solar is a 178.6 MW solar interconnection project in Androscoggin, Maine with a current status of withdrawn. It is proposed to connect at 44.172365, -70.104225 CMP 115kv Line 212.
178.6 MWCapacity
WithdrawnStatus
MEMarket
SolarTechnology
Project facts
| Canonical name | Green Apple Solar |
|---|---|
| Queue ID | 1097 |
| Status | withdrawn |
| Source status | W |
| Market | ME |
| Technology | Solar |
| Capacity | 178.6 MW |
| State | Maine |
| County | Androscoggin |
| Point of interconnection | 44.172365, -70.104225 CMP 115kv Line 212 |
| Requested (queue) date | 2021-02-15 |
| Proposed in-service date | 2027-11-01 |
| Operational date | — |
| Withdrawn date | 2026-04-06 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.