Grinnell 115kV (GEN-2019-050)

Grinnell 115kV is a 50.0 MW solar interconnection project in Gove, Kansas with a current status of withdrawn. It is proposed to connect at Grinnell 115kV.

50.0 MWCapacity
WithdrawnStatus
KSMarket
SolarTechnology

Project facts

Canonical nameGrinnell 115kV
Queue IDGEN-2019-050
Statuswithdrawn
Source statusWITHDRAWN
MarketKS
TechnologySolar
Capacity50.0 MW
StateKansas
CountyGove
Point of interconnectionGrinnell 115kV
Requested (queue) date2019-05-24
Proposed in-service date
Operational date
Withdrawn date2022-04-13
Developer
Utility / transmission ownerSUNC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata