Hebron 69kV (AC2-023)

Hebron 69kV is a 45.8 MW solar interconnection project in Wicomico, Maryland with a current status of suspended.

45.8 MWCapacity
SuspendedStatus
Market
SolarTechnology

Project facts

Canonical nameHebron 69kV
Queue IDAC2-023
Statussuspended
Source statusSuspended
Market
TechnologySolar
Capacity45.8 MW
StateMaryland
CountyWicomico
Point of interconnection
Requested (queue) date2017-01-25
Proposed in-service date2027-06-30
Operational date
Withdrawn date
Developer
Utility / transmission ownerDPL

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectsuspendedhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata