Hemlock Hollow Wind (1292)

Hemlock Hollow Wind is a 87.9 MW wind interconnection project in Cattaraugus, New York with a current status of withdrawn. It is proposed to connect at Homer Hill - Dugan Rd 115kV.

87.9 MWCapacity
WithdrawnStatus
AMarket
WindTechnology

Project facts

Canonical nameHemlock Hollow Wind
Queue ID1292
Statuswithdrawn
Source status0
MarketA
TechnologyWind
Capacity87.9 MW
StateNew York
CountyCattaraugus
Point of interconnectionHomer Hill - Dugan Rd 115kV
Requested (queue) date2021-10-20
Proposed in-service date2024-07-31
Operational date
Withdrawn date
DeveloperLiberty Renewables Inc.
Utility / transmission ownerNM-NG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.