Hemlock Hollow Wind (C24-052-001)

Hemlock Hollow Wind is a 95.0 MW wind interconnection project in Cattaraugus, New York with a current status of active. It is proposed to connect at Dugan - Homer Hill 115kV, Line #155.

95.0 MWCapacity
ActiveStatus
AMarket
WindTechnology

Project facts

Canonical nameHemlock Hollow Wind
Queue IDC24-052-001
Statusactive
Source status6
MarketA
TechnologyWind
Capacity95.0 MW
StateNew York
CountyCattaraugus
Point of interconnectionDugan - Homer Hill 115kV, Line #155
Requested (queue) date2024-08-01
Proposed in-service date
Operational date
Withdrawn date
DeveloperLiberty Renewables Inc.
Utility / transmission ownerNM-NG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata