Hobbs-Andrews 345kV Line (ERAS-2025-014)

Hobbs-Andrews 345kV Line is a 159.5 MW gas interconnection project in Hobbs, New Mexico with a current status of active. It is proposed to connect at Hobbs-Andrews 345kV Line.

159.5 MWCapacity
ActiveStatus
NMMarket
GasTechnology

Project facts

Canonical nameHobbs-Andrews 345kV Line
Queue IDERAS-2025-014
Statusactive
Source statusIA PENDING
MarketNM
TechnologyGas
Capacity159.5 MW
StateNew Mexico
CountyHobbs
Point of interconnectionHobbs-Andrews 345kV Line
Requested (queue) date2025-10-02
Proposed in-service date2029-06-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-03operational_date2028-05-31—medium
2026-10-03proposed_online_date—2029-06-01medium
2026-10-03statusoperationalactivehigh
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata