Hot Springs-Camas Prairie Substations Load Addition (L0633)

Hot Springs-Camas Prairie Substations Load Addition is a 9.0 MW other interconnection project with a current status of active. It is proposed to connect at Hot Springs Substation.

9.0 MWCapacity
ActiveStatus
Market
OtherTechnology

Project facts

Canonical nameHot Springs-Camas Prairie Substations Load Addition
Queue IDL0633
Statusactive
Source statusSTUDY
Market
TechnologyOther
Capacity9.0 MW
State
CountySanders
Point of interconnectionHot Springs Substation
Requested (queue) date2024-10-21
Proposed in-service date2027-10-24
Operational date
Withdrawn date
DeveloperMission Valley Power
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.