Hunterstown 500 kV (A36)

Hunterstown 500 kV is a 830.0 MW gas interconnection project in Adams, Pennsylvania with a current status of operational.

830.0 MWCapacity
OperationalStatus
Market
GasTechnology

Project facts

Canonical nameHunterstown 500 kV
Queue IDA36
Statusoperational
Source statusIn Service
Market
TechnologyGas
Capacity830.0 MW
StatePennsylvania
CountyAdams
Point of interconnection
Requested (queue) date1999-01-27
Proposed in-service date
Operational date2003-07-31
Withdrawn date
Developer
Utility / transmission ownerME

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.