ID Queue Project 683 — Solar+Battery in Ada, Idaho

ID Queue Project 683 — Solar+Battery in Ada, Idaho is a 200.0 MW solar+battery interconnection project in Ada, Idaho with a current status of withdrawn. It is proposed to connect at BOBN–MPSN #3 230kV Line.

200.0 MWCapacity
WithdrawnStatus
IDMarket
Solar+BatteryTechnology

Project facts

Canonical nameID Queue Project 683 — Solar+Battery in Ada, Idaho
Queue ID683
Statuswithdrawn
Source statusWithdrawn
MarketID
TechnologySolar+Battery
Capacity200.0 MW
StateIdaho
CountyAda
Point of interconnectionBOBN–MPSN #3 230kV Line
Requested (queue) date2022-10-27
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerIdaho Power Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: idahopower-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.