ID Queue Project 776 — Battery in Canyon, Idaho

ID Queue Project 776 — Battery in Canyon, Idaho is a 196.9 MW battery interconnection project in Canyon, Idaho with a current status of active. It is proposed to connect at Zilog 138kV Substation.

196.9 MWCapacity
ActiveStatus
IDMarket
BatteryTechnology

Project facts

Canonical nameID Queue Project 776 — Battery in Canyon, Idaho
Queue ID776
Statusactive
Source statusActive
MarketID
TechnologyBattery
Capacity196.9 MW
StateIdaho
CountyCanyon
Point of interconnectionZilog 138kV Substation
Requested (queue) date2025-04-14
Proposed in-service date2028-06-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerIdaho Power Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-31phaseFSAFSlow
2026-08-31statuswithdrawnactivehigh
2026-08-17statusactivewithdrawnhigh
2026-08-03new_project—activehigh

Explore related data

Source last checked2026-11-23
Data last materially changed2026-11-23
Page data generated2026-11-26

Provenance: idahopower-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata