ID Queue Project 799 — Gas in Elmore, Idaho

ID Queue Project 799 — Gas in Elmore, Idaho is a 167.0 MW gas interconnection project in Elmore, Idaho with a current status of active. It is proposed to connect at Mayfield 230kV Substation Bus.

167.0 MWCapacity
ActiveStatus
IDMarket
GasTechnology

Project facts

Canonical nameID Queue Project 799 — Gas in Elmore, Idaho
Queue ID799
Statusactive
Source statusActive
MarketID
TechnologyGas
Capacity167.0 MW
StateIdaho
CountyElmore
Point of interconnectionMayfield 230kV Substation Bus
Requested (queue) date2026-03-23
Proposed in-service date2032-05-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerIdaho Power Company

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-17phaseCSRlow
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-28

Provenance: idahopower-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.