ID Queue Project 813 — Battery in Jerome, Idaho

ID Queue Project 813 — Battery in Jerome, Idaho is a 300.0 MW battery interconnection project in Jerome, Idaho with a current status of withdrawn. It is proposed to connect at Hunt 230kV Substation.

300.0 MWCapacity
WithdrawnStatus
IDMarket
BatteryTechnology

Project facts

Canonical nameID Queue Project 813 — Battery in Jerome, Idaho
Queue ID813
Statuswithdrawn
Source statusWithdrawn
MarketID
TechnologyBattery
Capacity300.0 MW
StateIdaho
CountyJerome
Point of interconnectionHunt 230kV Substation
Requested (queue) date2026-04-13
Proposed in-service date2028-06-30
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerIdaho Power Company

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-28phaseCS—low
2026-09-07phase—CSlow
2026-08-17phaseCRW—low
2026-08-03new_project—withdrawnhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: idahopower-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata