ID Queue Project 818 — Solar+Battery in Minidoka, Idaho

ID Queue Project 818 — Solar+Battery in Minidoka, Idaho is a 56.0 MW solar+battery interconnection project in Minidoka, Idaho with a current status of active. It is proposed to connect at Paul 138kV Substation.

56.0 MWCapacity
ActiveStatus
IDMarket
Solar+BatteryTechnology

Project facts

Canonical nameID Queue Project 818 — Solar+Battery in Minidoka, Idaho
Queue ID818
Statusactive
Source statusActive
MarketID
TechnologySolar+Battery
Capacity56.0 MW
StateIdaho
CountyMinidoka
Point of interconnectionPaul 138kV Substation
Requested (queue) date2026-04-15
Proposed in-service date2030-12-15
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerIdaho Power Company

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-28phaseCS—low
2026-09-07phase—CSlow
2026-08-17phaseCSR—low
2026-08-03new_project—activehigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: idahopower-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.