ID Queue Project G0821 — Gas in Cassia, Idaho
ID Queue Project G0821 — Gas in Cassia, Idaho is a 10.0 MW gas interconnection project in Cassia, Idaho with a current status of withdrawn. It is proposed to connect at BPA 138KV BRIDGE SUBSTATION.
10.0 MWCapacity
WithdrawnStatus
IDMarket
GasTechnology
Project facts
| Canonical name | ID Queue Project G0821 — Gas in Cassia, Idaho |
|---|---|
| Queue ID | G0821 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | ID |
| Technology | Gas |
| Capacity | 10.0 MW |
| State | Idaho |
| County | Cassia |
| Point of interconnection | BPA 138KV BRIDGE SUBSTATION |
| Requested (queue) date | 2022-11-14 |
| Proposed in-service date | 2025-12-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Bonneville Power Administration |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata