ID Queue Project PIS007 — Solar in Bonneville, Idaho

ID Queue Project PIS007 — Solar in Bonneville, Idaho is a 107.0 MW solar interconnection project in Bonneville, Idaho with a current status of withdrawn. It is proposed to connect at Goshen-Rigby transmission line.

107.0 MWCapacity
WithdrawnStatus
IDMarket
SolarTechnology

Project facts

Canonical nameID Queue Project PIS007 — Solar in Bonneville, Idaho
Queue IDPIS007
Statuswithdrawn
Source statusWithdrawn
MarketID
TechnologySolar
Capacity107.0 MW
StateIdaho
CountyBonneville
Point of interconnectionGoshen-Rigby transmission line
Requested (queue) date2022-05-31
Proposed in-service date2025-11-30
Operational date
Withdrawn date
Developer
Utility / transmission ownerPacifiCorp

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.