Internal noncontrollable ETU from NMISA to Pittsfield ME (737)

Internal noncontrollable ETU from NMISA to Pittsfield ME is a 1,200.0 MW generation interconnection project in Somerset And Penobscot, Maine with a current status of withdrawn. It is proposed to connect at Emera Keene Rd substation and CMP Section 3023 345 kV Line.

1,200.0 MWCapacity
WithdrawnStatus
MEMarket
GenerationTechnology

Project facts

Canonical nameInternal noncontrollable ETU from NMISA to Pittsfield ME
Queue ID737
Statuswithdrawn
Source statusW
MarketME
TechnologyGeneration
Capacity1,200.0 MW
StateMaine
CountySomerset And Penobscot
Point of interconnectionEmera Keene Rd substation and CMP Section 3023 345 kV Line
Requested (queue) date2018-04-12
Proposed in-service date2021-12-31
Operational date
Withdrawn date2019-02-07
Developer
Utility / transmission ownerISO-NE

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.