Internal noncontrollable ETU to Larabee Road - increase (see Q740) (741)
Internal noncontrollable ETU to Larabee Road - increase (see Q740) is a 200.0 MW generation interconnection project in Lewiston, Maine with a current status of withdrawn. It is proposed to connect at Larrabee Road 345 kV Substation in Lewiston, Androscoggin county Maine 04240..
200.0 MWCapacity
WithdrawnStatus
MEMarket
GenerationTechnology
Project facts
| Canonical name | Internal noncontrollable ETU to Larabee Road - increase (see Q740) |
|---|---|
| Queue ID | 741 |
| Status | withdrawn |
| Source status | W |
| Market | ME |
| Technology | Generation |
| Capacity | 200.0 MW |
| State | Maine |
| County | Lewiston |
| Point of interconnection | Larrabee Road 345 kV Substation in Lewiston, Androscoggin county Maine 04240. |
| Requested (queue) date | 2018-04-12 |
| Proposed in-service date | 2021-12-31 |
| Operational date | — |
| Withdrawn date | 2020-11-29 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.