J2256 POI - Irvington 345kV line (J2988)

J2256 POI - Irvington 345kV line is a 175.0 MW wind interconnection project in Humboldt, Iowa with a current status of operational. It is proposed to connect at J2256 POI - Irvington 345kV line.

175.0 MWCapacity
OperationalStatus
Market
WindTechnology

Project facts

Canonical nameJ2256 POI - Irvington 345kV line
Queue IDJ2988
Statusoperational
Source statusActive
Market
TechnologyWind
Capacity175.0 MW
StateIowa
CountyHumboldt
Point of interconnectionJ2256 POI - Irvington 345kV line
Requested (queue) date2022-09-14
Proposed in-service date2025-03-15
Operational date2025-03-15
Withdrawn date
Developer
Utility / transmission ownerMIDAMERICAN ENERGY CO.

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.