Jamestown 345 kV (J2518)

Jamestown 345 kV is a 200.0 MW battery interconnection project in LaMoure, North Dakota with a current status of withdrawn. It is proposed to connect at Jamestown 345 kV.

200.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameJamestown 345 kV
Queue IDJ2518
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity200.0 MW
StateNorth Dakota
CountyLaMoure
Point of interconnectionJamestown 345 kV
Requested (queue) date2022-09-13
Proposed in-service date2024-11-01
Operational date2024-11-01
Withdrawn date2025-10-07
Developer
Utility / transmission ownerOtter Tail Power Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.