Jawbone Wind Project (58175_JWPI)

Jawbone Wind Project is a 80.0 MW wind interconnection project in Wheatland, Montana with a current status of active.

80.0 MWCapacity
ActiveStatus
NWMTMarket
WindTechnology

Project facts

Canonical nameJawbone Wind Project
Queue ID58175_JWPI
Statusactive
Source status(U) Under construction, less than or equal to 50 percent complete
MarketNWMT
TechnologyWind
Capacity80.0 MW
StateMontana
CountyWheatland
Point of interconnection—
Requested (queue) date—
Proposed in-service date2029-12-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerTriple Oak Power LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—activehigh

Explore related data

Source last checked2026-11-01
Data last materially changed2026-11-01
Page data generated2026-11-26

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.