Juniper Canyon 2 (G0242)

Juniper Canyon 2 is a 90.0 MW solar interconnection project in Klickitat, Washington with a current status of operational. It is proposed to connect at Horse Heaven-Harvalum 230 kV line.

90.0 MWCapacity
OperationalStatus
WAMarket
SolarTechnology

Project facts

Canonical nameJuniper Canyon 2
Queue IDG0242
Statusoperational
Source statusENERGIZED
MarketWA
TechnologySolar
Capacity90.0 MW
StateWashington
CountyKlickitat
Point of interconnectionHorse Heaven-Harvalum 230 kV line
Requested (queue) date2006-10-10
Proposed in-service date
Operational date2020-12-31
Withdrawn date
DeveloperAvangrid Power, LLC
Utility / transmission ownerBonneville Power Administration

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.