Kenowa to Nelson Rd. 345kV (J2619)

Kenowa to Nelson Rd. 345kV is a 140.0 MW solar interconnection project in Montcalm, Michigan with a current status of withdrawn. It is proposed to connect at Kenowa to Nelson Rd. 345kV.

140.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology

Project facts

Canonical nameKenowa to Nelson Rd. 345kV
Queue IDJ2619
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologySolar
Capacity140.0 MW
StateMichigan
CountyMontcalm
Point of interconnectionKenowa to Nelson Rd. 345kV
Requested (queue) date2022-09-15
Proposed in-service date2028-09-30
Operational date2028-09-30
Withdrawn date2026-10-20
Developer—
Utility / transmission ownerMETC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-11-05withdrawn_date—2026-10-20high
2026-11-05statusoperationalwithdrawnhigh
2026-10-31phasePhase 2Phase 3low
2026-10-14phasePhase 1Phase 2low
2026-07-29new_project—operationalhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata