Kent County - NG WRI DG Area Study #2 >5 MW (1041)

Kent County - NG WRI DG Area Study #2 >5 MW is a 49.8 MW solar interconnection project in Kent, Rhode Island with a current status of withdrawn. It is proposed to connect at NG Kent County Substation, feeders 3309 and 3310.

49.8 MWCapacity
WithdrawnStatus
RIMarket
SolarTechnology

Project facts

Canonical nameKent County - NG WRI DG Area Study #2 >5 MW
Queue ID1041
Statuswithdrawn
Source statusW
MarketRI
TechnologySolar
Capacity49.8 MW
StateRhode Island
CountyKent
Point of interconnectionNG Kent County Substation, feeders 3309 and 3310
Requested (queue) date2020-08-19
Proposed in-service date2025-07-07
Operational date
Withdrawn date2025-06-13
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.