Kit Carson Co-Op (69042_AMBES)

Kit Carson Co-Op is a 12.9 MW battery interconnection project in Taos, New Mexico with a current status of operational.

12.9 MWCapacity
OperationalStatus
PNMMarket
BatteryTechnology

Project facts

Canonical nameKit Carson Co-Op
Queue ID69042_AMBES
Statusoperational
Source status(OP) Operating
MarketPNM
TechnologyBattery
Capacity12.9 MW
StateNew Mexico
CountyTaos
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2025-12-01
Withdrawn date—
Developer—
Utility / transmission ownerSolar DG NM Amalia, LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata