Lake Charles Bulk 38kV Tap (S1050)

Lake Charles Bulk 38kV Tap is a 165.0 MW generation interconnection project in Jefferson Davies, Louisiana with a current status of withdrawn. It is proposed to connect at Lake Charles Bulk 38kV Tap.

165.0 MWCapacity
WithdrawnStatus
Market
GenerationTechnology

Project facts

Canonical nameLake Charles Bulk 38kV Tap
Queue IDS1050
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyGeneration
Capacity165.0 MW
StateLouisiana
CountyJefferson Davies
Point of interconnectionLake Charles Bulk 38kV Tap
Requested (queue) date2024-04-04
Proposed in-service date2026-05-31
Operational date2026-05-31
Withdrawn date2024-07-12
Developer
Utility / transmission ownerENTERGY ARKANSAS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata