Lansing - Postville (DPC) 161kV (J3527)

Lansing - Postville (DPC) 161kV is a 136.0 MW wind interconnection project in Allamakee, Iowa with a current status of withdrawn. It is proposed to connect at Lansing - Postville (DPC) 161kV.

136.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameLansing - Postville (DPC) 161kV
Queue IDJ3527
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity136.0 MW
StateIowa
CountyAllamakee
Point of interconnectionLansing - Postville (DPC) 161kV
Requested (queue) date2024-04-16
Proposed in-service date2027-03-01
Operational date2027-03-01
Withdrawn date2025-12-23
Developer
Utility / transmission ownerITC MIDWEST

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata