Leland Olds 345kV Substation (ERAS-2025-011)

Leland Olds 345kV Substation is a 750.0 MW gas interconnection project in Stanton, North Dakota with a current status of operational. It is proposed to connect at Leland Olds 345kV Substation.

750.0 MWCapacity
OperationalStatus
NDMarket
GasTechnology

Project facts

Canonical nameLeland Olds 345kV Substation
Queue IDERAS-2025-011
Statusoperational
Source statusERAS
MarketND
TechnologyGas
Capacity750.0 MW
StateNorth Dakota
CountyStanton
Point of interconnectionLeland Olds 345kV Substation
Requested (queue) date2025-10-01
Proposed in-service date
Operational date2029-09-27
Withdrawn date
Developer
Utility / transmission ownerBEPC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.