LH252W (LG-23-3-1)

LH252W is a 252.0 MW wind interconnection project in Grant County, New Mexico with a current status of active. It is proposed to connect at Hidalgo-Luna 345 kV line.

252.0 MWCapacity
ActiveStatus
NMMarket
WindTechnology

Project facts

Canonical nameLH252W
Queue IDLG-23-3-1
Statusactive
Source statusLGIA in breach
MarketNM
TechnologyWind
Capacity252.0 MW
StateNew Mexico
CountyGrant County
Point of interconnectionHidalgo-Luna 345 kV line
Requested (queue) date2023-03-14
Proposed in-service date2028-05-31
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerEl Paso Electric Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_project—activehigh

Explore related data

Source last checked2026-11-23
Data last materially changed2026-11-23
Page data generated2026-11-26

Provenance: epe-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.